The Baseline Forecast import follows the same logic with the following differences:

  • Imports Resource Assignment Expense spread data from the P6 Project Baseline.

  • The P6 WBS to EcoSys Cost Object mapping is implemented with the WBS Hierarchy Path rather than the P6 WBS Object ID. This is necessary since the Object ID’s change when the Baseline is created in P6.