The P6 Percent Complete import will update P6 % Complete at the Project and WBS level.
It assumes that the P6 Summarizer process has been run on the P6 Project to have accurate % Complete values.
-
Connect Job: P6 Percent Complete Import
-
EcoSys Action: ITG P6 Percent Complete Import
-
Dependencies: P6 Project and WBS Import
The EcoSys Cost Object External Key field is used to update from the P6 WBS Object ID.
Project level mapping follows the logic described in the section Map an existing EcoSys Project to a P6 Project.
Field Mappings
The default behavior of the % Complete import is to import the following P6 % Complete fields. If required, you can import any available P6 % Complete fields by modifying the Connect Job.
EcoSys Field |
EcoSys Subject Area |
P6 Field |
---|---|---|
External Key |
Cost Object |
WBS Object Id |
P6 Budget At Completion Cost |
Custom Field (Number) |
Summary Budget At Completion by Cost |
P6 Earned Value Cost |
Custom Field (Number) |
Summary Earned Value |
P6 % Complete |
Custom Field (Percent) |
Summary Cost Percent Complete |
P6 Performance % Complete |
Custom Field (Percent) |
Summary Performance Percent Complete |