Create or Update P6 WBS to EcoSys - EcoSys - 1.1 - Connectors & Integration - Hexagon

Integrating EcoSys with P6 Connector (1.1)

ft:locale
en-US
Product
EcoSys
Search by Category
Connectors & Integration
EcoSys Version
1.1

This job will import P6 Projects and WBS to EcoSys. This requires that the EcoSys and P6 Projects have already been mapped in the Project Setup process, see Map an existing EcoSys Project to a P6 Project. This jobs performs the following functions:

  • Update the EcoSys Project record

  • Create or Update P6 WBS to EcoSys Cost Objects

The P6 WBS and EcoSys Cost Object are mapped by assigning the P6 Object Id to the EcoSys WBS Cost Object External Key field.

  • Connect Job: P6 Project and WBS Import

  • EcoSys Action: ITG P6 Project WBS Import

At the WBS level, Structure Type category will be set to “PRJ” if the Scheduler Method is “External Schedule 1:1 WBS”. If the Scheduler Method is “External Schedule WBS Mapping”, then it will be “SCH”.

Field Mappings

The following table shows the field mapping for the Project update part of the job:

EcoSys Field

EcoSys Subject Area

P6 Field

Cost Object ID

Cost Object

N/A

Cost Object Name

Cost Object

Project Name

P6 Project Status (ID)

Cost Object Category

Project Status

P6 Project (ID)

Cost Object Category

Project Id

P6 Object Id

Custom Field (Text)

Project Object Id

The following table shows the field mapping for the WBS create/update part of the job:

EcoSys Field

EcoSys Subject Area

P6 Field

Cost Object ID

Cost Object

WBS Code

Cost Object Name

Cost Object

WBS Name

Hierarchy Path ID

Cost Object

Calculated based on the WBS parent/child relationship

External Key

Cost Object

WBS Object Id