The following table shows the mapping of a Connect job to EcoSys Action, and any relevant settings for that Job. Jobs that are part of the default P6 Connector configuration have been indicated.

Connect Job

EcoSys Action

Connect Job Setting

EcoSys CO Cat to P6 Activity Code

ITG CO Category to P6 Activity Code

Export EcoSys Cost Object Categories to P6 Activity Codes specified by the EcoSys Connect Global Setting list: "P6Connector.COCategoryToActivityCode"

EcoSys CO Cat to P6 Project Code

ITG CO Category to P6 Project Code

Export EcoSys Cost Object Categories to P6 Project Codes specified by the EcoSys Connect Global Setting list: "P6Connector.COCategoryToProjectCode"

EcoSys Resource Cat to P6 Resource Code

ITG P6 Resource Category to Resource Cod

Export EcoSys Resource Categories to P6 Resource Codes specified by the EcoSys Connect Global Setting list: "P6Connector.ResourceCategoryToResourceCode"

EcoSys Task Cat to P6 Activity Code

ITG Task Category to P6 Activity Code

Export EcoSys Task Categories to P6 Activity Codes specified by the EcoSys Connect Global Setting list: "P6Connector.TaskCategoryToActivityCode"

EcoSys Trans Cat to P6 Resource CodeEcoSys

ITG Trans Category to P6 Resource Code

Export EcoSys Transaction Categories to P6 Resource Codes specified by the EcoSys Connect Global Setting list: "P6Connector.TransactionCategoryToResourceCode"