This section describes all the integration jobs included in the P6 Connector. All parameters, field mappings, and other relevant details are included.

EcoSys Connect Job Naming Convention

In general, the naming convention followed for P6 Connector Jobs is to include the subject area for the source and target in the job name.

For example, "P6 Activity Code to Task Category" would import P6 Activity Codes to EcoSys Task Categories. This keeps the naming convention simple and obvious to understand the purpose of the job.

EcoSys Connect Job Action Naming Convention

P6 Connector also comes with pre-configured EcoSys Actions for each Connect Job. By convention, the EcoSys Action name will be the same as the Connect Job, with an "ITG" prefix.

For example, "ITG P6 Activity Code to Task Category".