Screen/Function |
Impact |
Description |
---|---|---|
Material Issue Report |
Data inconsistency |
If a Picklist already exists in Jovix with the same name as Smart Materials MIR name then, while integrating the MIR from Smart Materials the line items are added to existing Jovix Picklist. |
Material Issue Report |
Data inconsistency |
When a user adds additional Picklist items (in Jovix) for a Picklist that is already synced with Smart Materials. |
Unite of Measure |
Data inconsistency |
If a unit (quantity) is not assigned to a line item that is part of a Purchase Order or Material Receive Report. |
Purchase Order |
Data inconsistency |
Condition: For a Reverse Approved PO in Smart Materials. Scenario: A user changes the Unit of Measure of a line item to Quantity in Smart Materials. When the user transfers the ownership of the PO to Jovix, since the catalog item is already available in Jovix, the new Unit of Measure, Quantity, is not updated in Jovix. |
MRR/MIR/MTR/RTI |
Data not in sync between Smart Materials and Jovix |
Scenario: Consider an MRR is created in Smart Materials from Jovix. If the MRR is un-posted in Smart Materials, the un-posted MRR is not synced in Jovix. This is true for MIR, MTR, and RTI as well. |
Reverse Approved PO |
Data inconsistency |
Condition: A Receipt is created in Jovix but is not synced in Smart Materials. A user can Reverse Approve the PO in Smart Materials even while the ownership of the PO is with Smart Materials. |
Return to Inventory |
Data inconsistency |
Rule: In Smart Materials, if an RTI is created against an MIR then Revision and Unpost buttons are disabled for the MIR. Scenario: When an RTI is integrated to Smart Materials from Jovix, the Revision and Unpost buttons for the corresponding MIR in Smart Materials are enabled. You can then create a supplement for the MIR. This is not as per the normal Smart Materials workflow. |
Project Name |
Data inconsistency |
Project Name must be unique across all Jovix instances. |
Material Register |
Manual creation |
In Material Register, user is able to split quantity. For now, the split done in Jovix through Material Register must be manually created in Smart Materials. |
Release Notes |
Data not in sync between Smart Materials and Jovix. |
For an approved RN, the containers created and materials added in Smart Materials are not be reflected in Jovix. |