When an integration is triggered from Smart Materials, an Oracle DBMS job is created for each integration request. The mi_jvx_pck_config_custom.get_parallel_job_count function returns the number of jobs to be scheduled to run in parallel for each Smart Materials project and the default job count is 2. All other requests are placed in a queue. However, you can change the default job count by changing the return value of this function.

For more information about the queue mechanism, see Queue mechanism.

CIP- get_parallel_job_count