If you have necessary permissions, you can modify the duration of a work package or work step. Simply drag the work package or work step bar to the required position, the application updates it’s duration automatically.
-
Click Schedule Management > Production Planning .
-
Adjust the Time range, View format, and Current view period as necessary.
For more information, see View production plan.
-
Click a work package or work step bar and from the pop-up menu of the container, you can do the following.
If you want to do this
Then click this
View details of a work package or work step.
Update the progress of a work package or work step.
Click the corresponding Options menu on the bar and then select the necessary option. For example, to edit a work package, select the work package and click Options > Edit.
-
To update the duration of a work package or work step, drag the edge of the work package or work step bar to the required date.
You cannot reduce the duration of a work package in such a way that one or more work steps goes beyond the container.
-
Click Save and continue editing.
-
If a parent work package is closed, you cannot update the duration of the corresponding child work steps.
-
In the 1 week Time range view, you can drag a work step and adjust its duration to a specific time of the day.
What's next?
You need to update the schedule to save the changes that you made to the production planning timeline.