If the schedule and cost items are already mapped
-
On the left bar, click Smart Mapping > 5D Management .
-
Click Edit CDW% on the top-right corner of the page to edit the weightages.
-
In the left panel, browse and select the cost item.
The software highlights the mapped schedule items.
-
In the right panel, enter the weightages for work packages.
-
In the middle panel, click Save.
-
In the Update cost distribution weightage pop-up window, click Continue.
Notice that the cost item reflects the total distributed weightage.
You can also distribute the weightages while mapping
-
Click Edit CDW% on the top-right corner of the page to edit the weightages.
-
In the left panel, browse and select the cost item.
-
On the cost item that you want to map, click Options > Add mapping > Schedule.
-
In the right panel, browse and select a work package.
-
Enter a weightage for the work package.
-
In the middle panel, click Map.
Notice that the cost item is mapped to the work package and also reflects the weightage that you assigned.