Scenario: After having a look at the Project Schedule widget, you want to see and visualize detailed progress and look ahead planning. You must run 4D or 5D visualization to achieve the same. |
-
Click Schedule Management > Smart Visualization .
-
In the 4D/5D Visualization box, choose Planned.
-
In the View box, choose Schedule.
-
Select today's date as Start Date and a date after two weeks as End Date.
-
On the Visualization panel below the model, click Start on the animation control bar.
The model elements are color-coded by work package state within the selected time frame as the animation progresses.
-
Review and analyze the chart and animation.