Progress by installed quantities is one of the ways to update the real time progress based on the elements constructed/installed. This can be used for work packages which has linked elements that are countable (for example columns).
Before proceeding, make sure you have created a Level 3 South Column work package and Digital Layout of Formwork work step under it.
-
On the hamburger menu, click Schedule Management > My Work Packages.
-
On the Level 3 South Column > Digital Layout of Formwork work step, click Options and select Update Progress.
-
For Quantity, enter 17.
-
Click UPDATE and repeat the process for other work packages.
As the work package is dependent on work steps, when you update a work step progress, the application automatically updates the progress the work package based on installed quantity.
-
Navigate to Schedule Management > Scheduling, click Options and then select Generate Cost Progress.
-
Once the cost progress is generated successfully, click Publish to Cost System.