Update the work progress by installed quantities - HxGN Smart Build - 4.0 U10 (4.0.10) - Training

HxGN Smart Build Controls Training

Language
English
Product
HxGN Smart Build
Subproduct
Controls
Search by Category
Training

Progress by installed quantities is one of the ways to update the real time progress based on the elements constructed/installed. This can be used for work packages which has linked elements that are countable (for example columns).

Before proceeding, make sure you have created a Level 3 South Column work package and Digital Layout of Formwork work step under it.

  1. On the hamburger menu, click Schedule Management > My Work Packages.

  2. On the Level 3 South Column > Digital Layout of Formwork work step, click Options and select Update Progress.

  3. For Quantity, enter 17.

  4. Click UPDATE and repeat the process for other work packages.

    As the work package is dependent on work steps, when you update a work step progress, the application automatically updates the progress the work package based on installed quantity.

  5. Navigate to Schedule Management > Scheduling, click Options and then select Generate Cost Progress.

  6. Once the cost progress is generated successfully, click Publish to Cost System.