View the details of work package and update its progress - HxGN Smart Build - 4.0 U10 (4.0.10) - Training

HxGN Smart Build Controls Training

Language
English
Product
HxGN Smart Build
Subproduct
Controls
Search by Category
Training

Compact view

  1. On the hamburger menu, click Schedule Management > Production Planning .

  2. Enter the following details:

    • Time Range - 2 Weeks

    • View Format - Compact

    • Current view period - May 23, 2022 - May 29, 2022

  3. Click Edit on the top right corner, and navigate to the Level 14 South Columns work package.

  4. Click Options on the Level 14 South Columns work package and click Edit.

  5. Change the Planned End Date to May 26, 2022 5:00 PM and then click Save.

  6. Now, place the cursor on the right border of the Stripping work step and drag it till May 27, 2022 5:00 PM.

  7. You can see a dynamic tooltip that displays time while dragging the work step bar. With the help of the tooltip, you can drag the work step bar to a specific time.

  8. Similarly, drag the QA or Acceptance work step till May 27, 2022 5:00 PM.

  9. Click Save.

  10. Move your mouse on the Stripping work step.

    The application displays its details in the tooltip.

Detailed view

  1. On the hamburger menu, click Schedule Management > Production Planning .

  2. Enter the following details:

    • Time Range - 6 Weeks

    • View Format - Detailed

    • Current view period - February 21, 2022 ā€“ April 03, 2022

  3. Click Edit on the top right corner, and navigate to the Level 1 South Columns work package.

    You can see the detailed schedule of the Level 1 South Columns work package including the resources assigned to its work steps.

  4. Click Options on the Level 1 South Columns work package and select Update Progress.

  5. Click Start and then click Edit.

  6. For the Place Concrete work step progress, enter 50.

  7. Similarly, enter progress percentages for the remaining work steps.

  8. Click SAVE & UPDATE.

    You've successfully updated the progress of the Level 1 South Columns work package and Place Concrete work step.