On the hamburger menu, click Schedule Management > Production Planning .
-
Enter the following details:
-
Time Range - 2 Weeks
-
View Format - Compact
-
Current view period - May 23, 2022 - May 29, 2022
-
-
Click Edit on the top right corner, and navigate to the Level 14 South Columns work package.
-
Click Options on the Level 14 South Columns work package and click Edit.
-
Change the Planned End Date to May 26, 2022 5:00 PM and then click Save.
-
Now, place the cursor on the right border of the Stripping work step and drag it till May 27, 2022 5:00 PM.
-
You can see a dynamic tooltip that displays time while dragging the work step bar. With the help of the tooltip, you can drag the work step bar to a specific time.
-
Similarly, drag the QA or Acceptance work step till May 27, 2022 5:00 PM.
-
Click Save.
-
Move your mouse on the Stripping work step.
The application displays its details in the tooltip.
Detailed view
-
On the hamburger menu, click Schedule Management > Production Planning .
-
Enter the following details:
-
Time Range - 6 Weeks
-
View Format - Detailed
-
Current view period - February 21, 2022 ā April 03, 2022
-
-
Click Edit on the top right corner, and navigate to the Level 1 South Columns work package.
You can see the detailed schedule of the Level 1 South Columns work package including the resources assigned to its work steps.
-
Click Options on the Level 1 South Columns work package and select Update Progress.
-
Click Start and then click Edit.
-
For the Place Concrete work step progress, enter 50.
-
Similarly, enter progress percentages for the remaining work steps.
-
Click SAVE & UPDATE.
You've successfully updated the progress of the Level 1 South Columns work package and Place Concrete work step.