Menu Path
Work > Projects > Compatible Units > Compatible Units Overhead Codes
Description
Include overhead costs in compatible units project estimates.
On this page you can perform these actions:
-
Define overhead costs for compatible units design projects
-
Apply overhead costs to the total estimates for compatible units design projects
For full access to the compatible units overhead codes features, there are five new org. options to configure.
Contact your system administrator to check your organization options:
Org. option |
Description |
CUESOVHD |
Determines if overheads will be applied during compatible units estimation. If set to NO, Compatible Units Overhead Codes are not considered when estimation is performed on a CU Estimate. If set to YES, Compatible Units Overhead Codes are included when estimation is performed. |
CUESSPMT |
Span multiplier factor: Determines the standard overage allowance for length-based parts that are included in a Compatible Units Library record that has been flagged as Span Only. When a valid value is specified, this value is divided by 100 (%), and applied to the Quantity of parts in the compatible units library record. |
CUESREMV |
Remove Labor calculation factor: When a valid value is specified and no applicable record exists for labor according to the Remove action type, this value is divided by 100 (%), and applied for the calculation of labor hours on a compatible units library record for the Remove action type of a Compatible Unit; based on a value specified for the Install labor function. |
CUESTRFR |
Transfer labor calculation factor: When a valid value is specified and no applicable record exists for labor according to the Transfer action type, this value is divided by 100 (%), and applied for the calculation of labor hours on a compatible units library record for the Transfer action type of a Compatible Unit; based on a value specified for the Install labor function. |
CUESFERC |
Determines if the FERC Unit Estimate will be generated during compatible units estimation. If set to NO, the FERC Unit Estimate is not generated. If set to YES, the FERC Unit Estimate is generated when estimation is performed. |
Related topics