Viewing the resource load - HxGN EAM - 12.0.1 - Help - Hexagon

HxGN EAM Help

Language
English
Product
HxGN EAM
Search by Category
Help
HxGN EAM Version
12.0.1

View the resource loading required for the current PM forecasting session to determine the number of resource days required to complete the work. View the number of estimated hours and resource days required by trade per month, week, or day in the forecasting session. Modify the date ranges to plan PMs for a specific time period, and then make changes to the underlying PM forecasting session to balance the resource load. This popup considers both Released and Forecasted PMs.

To view the resource load:

  1. Select Work > WO Planning > PM Forecasting.

  2. Choose to create a new PM forecasting session or work with an existing PM forecasting session.

  3. Click View Resource Load.

  4. Specify this information:

    Start Date - Specify the starting date for the current PM forecasting session.

    End Date - Specify the ending date for the current PM forecasting session. Work Hours per Day are automatically populated based on the value on the Parameters page.

    Specify one of the following options:

    • Group by Day - Specify to group the defined date range by days.

      The time period is displayed in days. Group Start Date matches Group End Date for each record. Estimated Hours, Resource Day Requirements, and Total Resource Day Requirements are calculated by this selection.

    • Group by Week - Specify to group the defined date range by weeks.

      The time period is displayed in weeks. Estimated Hours, Resource Day Requirements, and Total Resource Day Requirements are calculated by this selection.

    • Group by Month - Specify to group the defined date range by month.

      The date range records are displayed until the End Date is the same as Group End Date.

      Resource Days Required is calculated as:

      Resource Days Required = Estimated Hours ∕ Work Hours per Day

      Resource Days Required is calculated as the number of person-days required for the trade for the defined date range.

  5. View the current resource load. Modify the PM due dates in the underlying PM forecasting session.

  6. Click Refresh Resource Data. Date Last Refreshed is automatically populated and the data on the popup is refreshed based on the current PM forecasting session.

  7. Click Close.

    The changes to the PM forecasting session made while the View Resource Load popup is open are not automatically displayed. To view the changes made in the grid, click Refresh Resource Data.