Workflow Event Processing > Sequential - HxGN EAM - 12.1 - Feature Briefs - Hexagon

HxGN EAM Approval Workflows

Language
English
Product
HxGN EAM
Search by Category
Feature Briefs
HxGN EAM Version
12.1

Action: For purchase order 10002, the buyer moves the PO status from ‘Unfinished’ to ‘Awaiting Approval’.

  1. The system captures the Parameter Definition values for the purchase order.

    Parameter

    Column

    Alias

    Value

    1

    ORD_CODE

    PO

    10002

    2

    ORD_DESC

    PO Desc.

    Capital Expenditure | Purchase of New Asset

    3

    ORD_TOTAL

    PO Total

    50,000

    4

    ORD_ORG

    Organization

    ORG1

    5

    ORD_STORE

    Store

    STORE-01

  2. Since the Activation Condition of Organization is met, the system creates the workflow event and approval steps.

    Sequence

    User

    Status

    Completed By

    1

    SUPERVISOR

    Pending

    2

    MANAGER

    Pending; Contingent

    3

    VP

    Pending; Contingent

  3. Since the Approval Flow Type is Sequential, the first Approval Step where Step Conditions are met is added in the ‘Pending’ status. All subsequent steps are added in the ‘Pending; Contingent’ status.

    The Manager and VP users are not able to approve until the previous steps have been approved. Once the Supervisor approves his step, the Manager approval step will be updated to ‘Pending’, and an email will send to the Manager if an E-mail Template is supplied on the Approval Step setup record.

    Sequence

    User

    Status

    Completed By

    1

    SUPERVISOR

    Approved

    SUPERVISOR

    2

    MANAGER

    Pending

    3

    VP

    Pending; Contingent