The ERP Adapter enables the EcoSys application to interact with SAP. Data can be exchanged bi-directionally between EcoSys and SAP. The supported subject areas are listed below:
Subject Area |
Data Exchange |
Uses Operation Type |
---|---|---|
Actual Costs and Revenue |
SAP to EcoSys |
Import Actuals |
CATS Timesheets (Unapproved, Approved, and External Hours) |
SAP to EcoSys |
Import Actuals |
Commitments |
SAP to EcoSys |
Import Forecast |
Planned Costs and Revenue |
SAP to EcoSys |
Import Forecast |
Project, WBS Structure, Networks, Network Activities |
SAP to EcoSys |
Import Cost Object |
Activity Elements and Work Orders |
SAP to EcoSys |
Import Cost Object |
Forecast Costs |
EcoSys to SAP |
Export Forecast |
Budget Totals |
SAP to EcoSys |
Import Forecast |
Details of Cost Data Imported from SAP
SAP Project |
Actual Cost Line Items |
Commitment Line Items |
Budget Totals |
Planned Cost Totals |
Planned Cost & Revenue Line Items |
Timesheets Internal |
Timesheets External |
---|---|---|---|---|---|---|---|
WBS Element |
ü |
ü |
ü |
ü |
ü |
ü |
ü |
Work Order |
ü |
ü |
|||||
Network Header |
ü |
ü |
|||||
Network Activity |
ü |
ü |
ü |
ü |
|||
Activity Element |
ü |
ü |
ü |
ü |
User Interface
Operations for import and export of data are initiated from the EcoSys web application. After the connection to SAP is configured, an administrator may configure one or more external operations. Operations perform the supported data exchange based on parameters supplied by the end-user. Parameters typically include filters for which projects, versions, and date ranges should be included in the data exchange. The relevant screens are listed below:
-
Integration > External Data Sources (for configuring the connection)
-
Integration > Operations (for configuring the specific import/export jobs)
-
System Info > Integration (for validating the connection)