After all time-phase settings have been applied, this procedure allows you to systematically spread costs, quantities, and hours for line items with the following Time-Phase Methods:
-
Back Loaded - Line items are spread with back-loaded curve
-
Bell Curve - Line items are spread with bell curve
-
Detail Settings - Time-phasing settings must be established at the line item level
-
Front Loaded - Line items are spread with front-loaded curve
-
Linear - Line items are spread linearly
-
Manual - The user manually defines time-phased values per period
-
Project Schedule - Line items spread as per the inputs given in project schedule method
-
Click the Actions list and select Time-Phase Open Budget.
-
Click the Project ellipsis and select required project.
The Project displayed in the toolbar at the top of the screen is the only project available for selection in the Time-Phase Open Budget dialog.
-
Click RUN.