This procedure allows you to establish change line items once the change header is created. These change line items can be added only to Scope, Budget, and Forecast changes. Change line items can be defined only for those objects with a Cost Control Level assignment.

Change line items can be established only for the change header with an Open status in the Change Register panel. If a project change has been submitted for approval or approved, the change must be rejected or re-opened to update the project change details.