To view the Planned vs Actual Details by Periods report, perform any of the following actions.
-
View the report in the Actuals screen:
-
Navigate to Progress > Actuals.
-
Click the Reports tab.
-
Click the Planned vs Actual Details by Periods tab.
-
Click the ellipsis for each of the below parameters and select the required values.
-
Click the Project ellipses and select the required project.
-
Click the Project Period ellipses and select the project period.
-
-
Type the number of Past Periods. The report Planned vs Actual Details by Periods appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Actuals > Planned vs Actual Details by Periods.
-
Click the ellipsis for each of the below parameters and select the required values.
-
Click the Project ellipses and select the required project.
-
Click the Project Period ellipses and select the project period.
-
-
Type the number of Past Periods. The report Planned vs Actual Details by Periods appears.
-