To view the Actual Details by Selected Periods report, perform any of the following actions.
-
View the report in the Actuals screen:
-
Navigate to Progress > Actuals.
-
Click the Reports tab.
-
Click the Actual Details by Selected Periods tab.
-
Click the ellipsis for each of the below parameters and select the required values.
-
Click the Project ellipses and select the required project. By default, the last selected project appears.
-
Click the Project Period ellipses and select the project period. By default, the last selected period appears.
-
-
Type the number of Past Periods.
-
Click the Run icon. The Actual Details by Selected Periods report appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Actuals > Actual Details by Selected Periods.
-
Click the ellipsis for each of the below parameters and select the required values.
-
Click the Project ellipses and select the required project. By default, the last selected project appears.
-
Click the Project Period ellipses and select the project period. By default, the last selected period appears.
-
-
Type the number of Past Periods.
-
Click the Run icon. The Actual Details by Selected Periods report appears.
-