This procedure allows you to view and unassign the Changes assigned to an Issue.
-
In the Issue Details panel, click the ISSUE CHANGE DETAILS tab.
-
By default, the last selected Issue appears in the Issue ellipsis. To change the Issue, click the Issue ellipsis in the toolbar and select the required Issue.
-
You can customize the view of the Related Changes panel from View Settings.
-
-
To unassign a Change, click its respective Disconnect hyperlink.
Issues can only be Disconnected if the Change Status is not in a Submitted or Approved State.