This process allows you to import all the WBS, Activities, External Dates, Relationships, Dates, Percent Complete and Forecast from P6 to a project.

  1. Click the Actions list and select Import External Schedule.

  2. Click the Project ellipsis and select the project to which you want to import the P6 project data.

    The project should have a P6 Project ID selected and also the P6 Project Import ID should be selected as Yes in Project Setup.

  3. Type the Comment related to project being imported.

  4. Click RUN.