If any changes are made to Cost, Hours, or any transaction in Resource Assignment, those changes are added in the Resource Assignment spreadsheet. Then, the delta hours and delta cost will be generated in the Baseline Compare spreadsheet.

This process allows you to create schedule change.

  1. Click the Actions list and select Create Schedule Change.

  2. Click the ellipsis and select the required values.

    • Project - Verify the project selected in Project.

    • Baseline - Select the baseline in which you want to save your original project details.

    • Change - Select the change that is created for the particular project in Change module.

  3. Type the Comments related to schedule change.

  4. Click RUN.

    create schedule change_4.11