This process will transfer the Resource Assignment transactions to the Original Budget. This includes time-phasing dates and curves.

  1. Click the Actions list and select Push Resource Assignments to OB.

  2. Click the Project ellipsis and select the project which you want to transfer its data to Original Budget.

  3. Click RUN.

    This action will reschedule the project object Start Date and End Date in Project Setup to the dates set in Project Scheduler tab.