View or Establish Project Structure - EcoSys - 4.11 - Help - Hexagon

EcoSys Projects Help (4.11)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.11

Follow the procedure below to setup a Project Schedule Activity.

  1. Navigate to Scheduling > Project Schedules.

  2. In the Project Schedule Register panel, do the following:

    1. (Optional) In the toolbar, click the Project Controller ellipsis to select the project controller.

      All the projects that are controlled by the selected project controller appear.

    2. (Optional) In the toolbar, click the Project Manager ellipsis to select the project manager of the project.

    3. (Optional) In the toolbar, click the Portfolio ellipsis to select the portfolio to which the project belongs to.

    4. Select the required Project ID hyperlink against the Project Schedule Activity scheduler method to view and edit its project details.

      The project details are displayed on the right-hand side.

  3. (Optional) To change the project within the same scheduler method, in the Project Activity panel, at the top of the screen, in the toolbar, click the Project ellipsis and select the required project.

  4. If required, click Refresh icon to update the screen.