This procedure allows you to update the project equipment rates.

  1. Click the RATE TABLES tab.

  2. In the Rates panel, click the Update Project Equipment Rates.

  3. Click the Insert Row icon to add a new labor rate.

  4. Click the ellipsis for each of the below boxes and select the required values.

    • Equipment ID

    • Currency

    • Transaction Category: Region

  5. Type the required Rate: Base.

  6. Click SAVE. The Equipment Name auto-populates based on the Equipment ID selected.

    Click the Delete Row(s) icon to delete the equipment rate.