This procedure allows you to update the project material rates.

  1. Click the RATE TABLES tab.

  2. In the Rates panel, click Update Project Material Rates.

  3. Click the Insert Row icon to add a new labor rate.

  4. Click the ellipsis for each of the below boxes and select the required values.

    • Material ID

    • Currency

    • Transaction Category: Region

  5. Type the required Rate: Base.

  6. Click SAVE. The Material Name auto-populates based on the Material ID selected.

    Click the Delete Row(s) icon to delete the material rate.