Estimate project reports are available via two different menu options in EcoSys Projects:
-
From Estimate Summary screen: To view the reports from the Estimate Summary screen, follow the procedure below.
-
Navigate to Estimating > Estimate Summary.
-
At the top of the screen, in the toolbar, click the Project ellipsis and select the required project to view all its estimate details.
-
Click the REPORTS tab.
-
Click the hyperlink of the required report.
-
-
From Reports menu: To view the reports from the Reports menu, follow the procedure below.
-
Navigate to Reports > Estimates.
-
Select the required report from the menu list. The report will be generated based on the last project selected.
-