Update and View S3D Model Design Progress - EcoSys - 4.03 - Help - Hexagon

EcoSys Projects Help (4.03)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.03

The S3D projects use S3D Progress method to update the Design Object Type properties for each project line item.

Update S3D Model Design Progress

This procedure allows you to import all the Design Object Type properties and its data to Earned Value screen. These properties are updated in the S3D Integration screen by the admin.

Also, this action will convert the Budgeted Quantity UOM to SI UOM's value. These values will be used in the overall EV Calculation.

After performing this action, the Earned Value screens must be manually refreshed.

  1. Navigate to Progress > Earned Value.

  2. Click the Project and Project Period ellipsis and select the required project details.

  3. Click the Actions list and select Update S3D Model Design Progress.

  4. Verify that the selected Project is the required project for which S3D Design Object Type properties needs to be updated.

  5. Click RUN and then OK.

View Quantity Budget by Design Object Type

This procedure allows you to view the Properties, Model Quantities, and % Rollup of project line items by Design Object ID.

  1. Click the Earned Value tab.

  2. In the Earned Value Summary panel, click the S3D Progress, Progress Method hyperlink.

  3. In the Quantity Budget by Design Object Type panel, click the Design Object Type ID hyperlink.

    The properties of project line items by Design Object ID are displayed in the Properties by Design Object ID panel.

  4. Click the S3D Model Quantity hyperlink.

    The model quantity of project line items by Design Object ID are displayed in the Model Quantity by Design Object ID panel.

  5. Click the S3D Rollup % Complete hyperlink.

    The % Rollup of project line items by Design Object ID are displayed in the % Rollup by Design Object ID panel.