Earned Schedule is the time planned to complete the activities.

To view the earned schedule parameters, click the Earned Schedule tab. The below listed details appear in the Earned Schedule panel:

  • Path ID - Displays the path ID of the object

  • Name - Displays the name of the of the object

  • BAC Hours - Displays the budget at completion hours of the object

  • BAC Cost - Displays the budget at completion cost of the object

  • Planned Value - Displays the planned value of the object

  • Earned Value - Displays the earned value of the object

  • Schedule Variance Cost - Displays the schedule variance cost of the object row

  • Schedule at Completion Days - Displays the difference between Budget Start Date and Budget End Date

  • Earned Schedule - Displays the time planned to complete the activity

  • Actual Duration - Displays the actual time taken to complete the activity

  • SV(t) - Displays the time difference between Earned Schedule and Actual Duration of the activity

  • SPI(t) - Displays the Schedule Performance Index value or percentage complete of the activity

  • Budget Start Date - Displays the budget start date

  • Current Budget End Date - Displays the budget end date

  • IEAC(t) - 1 - Displays the independent estimate at completion of the object. The formula is BAC/CPI.

  • IEAC(t) - 2 - Displays the independent estimate at completion of the object. The formula used to calculate IEAC2 Cost is AC + (BAC – EV/ (CPI*.8) + (SPU*.2).