This process allows you to view the Productivity Hours parameters and related charts.
-
Click the Productivity Hours tab. The productivity analysis costs appear in the Productivity Hours panel.
The below listed details appear in the Productivity Hours panel:
-
Path ID - Displays the path ID of the object.
-
Name - Displays the name of the of the object.
-
BAC Hours - Displays the budget at completion hours of the object.
-
PV Hours - Displays the present value hours of the object.
-
% Complete - Displays the percentage complete of the object.
-
EV AC Cost - Displays the sum of estimated actuals and actuals hours of the object.
-
EV Hours - Displays the earned value hours of the object.
-
CPI Hours - Displays the cost performance index hours of the object.
-
SPI Hours - Displays the schedule performance index hours of the object.
-
TCPI Hours - Displays to complete performance index hours of the object.
-
TSPI Hours - Displays to complete schedule performance indicator hours of the object.
-
Cost Variance - Displays the cost variance of the object.
-
Schedule Variance - Displays the schedule variance of the object row.
-
IEAC1 Hours - Displays the independent estimate at completion of the object. The formula is BAC/CPI.
-
IEAC2 Hours - Displays the independent estimate at completion of the object. The formula used to calculate IEAC2 Cost is AC + (BAC – EV/ (CPI*.8) + (SPU*.2).
-
IEAC3 Hours - Displays the independent estimate at completion of the object. The formula is AC + (BAC-EV/CPI*SPI).
-
IEAC4 Hours - Displays the independent estimate at completion of the object. The formula is AC + (BAC-EV).
-
-
To view the charts related to productivity hours,
-
View the project performance hours chart in the Project Performance Chart panel. The BAC, EV AC, and EV values appear in a bar chart format.
-
To view the performance variance chart or performance factor chart for specific objects, perform any of the following:
-
Click the CPI Cost hyperlink. The CPI and SPI costs specific to the object appear in a bar chart format.
-
Click the Cost Variance hyperlink. The cost variance and schedule variance specific to the object appear in a bar chart format.
-
-