This process allows you to view the resource allocation graph plotted between the Cost, Hours, Start Date and End Date for Schedule WBS activities.

This resource allocation graph displays both the data baseline and the scheduler, and you can compare both.

  1. Click the BASELINE tab.

  2. In the Activity Scheduler Baseline panel, select the task row for which you want to view the resource allocation graph.

  3. Click the RESOURCE ALLOCATION GRAPH - BASELINE tab.