To view the Actual Details by Alternate Structure report, perform any of the following actions.
-
View the report in the Actuals screen:
-
Navigate to Progress > Actuals.
-
Click the Reports tab.
-
Click the Actual Details by Alternate Structure hyperlink. A dialog box appears with a title Actual Details by Alternate Structure.
-
Click the Project ellipses to select the required project. By default, the last selected project appears.
-
Click the Alternate Structure ellipses to select the required project. By default, the last selected alternate structure appears.
-
Click the Run button. The preview of the report appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Actuals > Estimated Actual Details by WBS.
-
Click the Project ellipses to select the required project. By default, the last selected project appears.
-
Click the Alternate Structure ellipses to select the required project. By default, the last selected alternate structure appears.
-
Click the Run button. The preview of the report appears.
-