This procedure allows you to move back the production actuals from an open project period to staging and delete from production for a specified project. Once the production actuals are backed out, a log entry appears on the Log tab.

If the period has been closed, the production actuals will not be backed out.

  1. Navigate to Progress > Actuals.

  2. Click the Actions list and select Back Out Production Actuals.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    The Project displayed in the green parameter bar at the top of the screen is the only project available for selection in the Back Out Production Actuals dialog box.

  4. Click the Period ellipsis to select the required period. By default, the last selected period appears.

  5. (Optional) Type in the Comment.

  6. Click RUN and then OK.