This procedure allows you to add and schedule a new activity to a project object in the Spreadsheet tab.
-
Click the Activity Schedule tab and then click the Spreadsheet tab.
-
In the Activities Spreadsheet panel, click the Insert Row icon.
-
Click the Path ID-Name ellipsis and select the project to which you want to add an activity.
-
Type in the below fields for the newly created activity:
-
Activity ID
-
Activity Name
-
Duration
-
-
Click the Duration Units list and select the units.
-
Click the Actual Start Date and Actual Finish Date ellipsis and select the start and finish dates.
-
Select the % Complete Type from the list.
-
Click SAVE. The fields WBS ID, WBS Name, Actual Duration (Hrs), and % Complete are auto-populated.
-
An activity must be added to a CCL Path ID, else the column will appear in red.
-