Time-Phasing is a required process for line items when Time-Phase is checked in the Project Setup screen (Projects > Project Setup – General tab).

Time-phasing can be performed systematically by selecting the Refresh Time-Phased Forecast (Multi Project) action for the projects with all the curves except for manual curve.

  • Ensure that the End Date selected occurs after the Start Date. If not, the Time-Phased Cost cannot be calculated.

  • If the Project Exchange Rate Table is not established in Project Setup screen, then the system cannot calculate Cost in Project Currency.