This procedure allows you to update the adjustment methods in the Forecast tab.

If Time-Phase Settings adjustment method is assigned, then do not select Time-Phasing Method as Manual for that cost control object.

  1. Navigate to Forecasts > Forecast.

  2. Click the Forecast tab.

  3. Click the Adjustment Method ellipsis to select the required forecast method. The available adjustment methods are listed below:

    • Adjustment to Time-Phasing End

    • Adjustment to Next

    • Adjustment to Future Periods

    • Adjustment to Year End

  4. Type the number of Adjustment Periods for the cost control object with Adjustment to Future Periods adjustment method.

  5. Click the Save icon.