This procedure allows you to view or create a project schedule structure for a project.

  1. Click the Project Structure tab and then Project Structure Register tab.

  2. Right-click the rows list and select Insert Under. This creates a new row under the selected line item.

    Do not choose Insert or Insert Multiple options. If these options are used, the project structure will not be added as a part of the project unless the parent path ID is also specified.

    • The Insert Under option places the project structure below the selected line item.

    • If the Insert Row option is used, the project structure is placed at the same hierarchy as the selected line item.

  3. Type in a unique ID and Name for the project object.

  4. Click the Parent Path ID ellipsis and select the required parent.

    If you do not select parent path ID, EcoSys automatically selects the immediate parent available in the project structure after saving.

  5. Click the ICMS Cost Categories and Groups ellipsis and select the required category.

  6. Click the Calendar (ID) ellipsis and select the required calendar.

  7. Click the Save icon.

    • Click the Delete Row(s) icon to delete the selected row.

    • You can customize the view of the Maintain Project Structure spreadsheet from the view settings.