This procedure allows you to update the activity progress details.
-
In the Activity Scheduler panel, select the activity row for which you want to update progress details.
-
In the Progress panel, select the Actual Start Date.
-
Click the Progress Type list and select the required progress type.
If you want to calculate Remaining Duration:
-
Select Percent Complete as progress type.
-
Type the total percentage completed for the cost object / activity in the Percent Complete field.
By default, Percent Complete value is equal to total Weighted % Complete which is fetched from Weighted Steps.
-
Click SAVE.
For example,
Percent Complete = 20%
Original Duration = 400 hrs
Calculation for Remaining Duration = 400 - (400 * 0.20) = 320 hrs.
If you want to calculate Percent Complete:
-
Select Remaining Duration as progress type.
-
Type the remaining duration of the cost object in the Remaining Duration field.
-
Click the Remaining Duration Units list and select the units.
-
Click SAVE.
For example,
Actual Duration = 515 hrs
At Complete Duration = 630 hrs
Calculation for Percent Complete = 515 / 630 = 81.8%.
If you are using Weighted Steps to progress the activity, the Actual Start Date must be populated, and Progress Type needs to be set to Percent Complete.
-