This procedure allows you to view and update the general schedule details of each project cost object.

  1. In the Project Scheduler panel, select the cost object row for which you want to update general attributes.

  2. In the Project Scheduler Details panel, click the General tab.

  3. Type the number of hours/days required for the cost object in the Original Duration field.

  4. Select the units from the Duration Units list.

  5. Type in the Objective of the cost object.

  6. Click the Object Calendar ellipsis and select the calendar for the cost object.

    External fields will be populated by the P6 Integration.