This procedure allows you to add adjustments to the line items.

You can only add adjustments to the line items where the Cost Control Level is not marked as Y.

  1. In the Estimate Summary panel, click the Total Cost hyperlink. The bottom panel appears.

  2. In the bottom panel, click the Line Item Adjustments tab. All the line item details added to the project appear in the Adjustment Creation panel.

    By default, the last select object appears in the Object ellipsis. To change the existing object, click the Object ellipsis from the green parameter bar and select the required object.

    SHARED Tip You can filter the line items by selecting the Cost Account or Crew ellipsis in the Adjustment Creation panel.

  3. Perform any of the following actions:

    • Add the adjustment percentage. To add the adjustment percentage,

      1. Click the Adjustment Type ellipsis and select %.

      2. Type the required Adjustment %.

    • Add the direct adjustment. To add the direct adjustment,

      1. Click the Adjustment Type ellipsis and select Direct.

      2. Type the required Adjustment Direct.

  4. (Optional) Type the Adjustment Comments.

  5. Click the Save button. The Adjustment Cost and Total Cost in Object Currency auto-populate.