This procedure allows you to view all the other costs apart from material, labor, and equipment costs.

  1. Click the Other Costs tab.

  2. Click the Insert Row icon to add a new cost.

  3. Click the ellipsis to select the required values in the below fields:

    • Object Path ID: Select the required object.

    • Currency: Select the required currency.

  4. Type the required details of the cost:

    • Quantity: Type the quantity

    • Cost: Type the cost.

    • (Optional) Description: Type the description of the cost.

  5. Click the Save button.

    Click the Delete Row(s) icon to delete the cost.