Export Forecasts - EcoSys - Help - Hexagon

EcoSys Primavera P6 Adapter Help

ft:locale
en-US
Product
EcoSys
Search by Category
Help
EcoSys Version
9.2

The Export Forecasts screen enables you to run an export of forecast information to P6. Considerations for exporting Forecasts are listed below.

  • Data mappings and application settings must first be configured correctly to allow the export to take place.

  • Forecasts for a designated time period are exported.

  • Forecasts for a designated version in EcoSys are exported.

  • Forecasts can be exported using any of the following duration formats: Hour, Month, Week, Quarter, Year.

  • Forecasts can be exported in any currency, provided the currency exists in EcoSys.

  • This functionality allows the export of EcoSys working forecast transactions from Cost Objects into P6. The transactions are exported as resource assignments of a WBS Summary activity, under each project or WBS mapped to cost objects in EcoSys.