The Import % Complete screen within the Integration menu enables the user to run an import of % complete from P6.
-
You must create a custom field in EcoSys, to hold the % Complete values. This should be a Cost Object Level custom field.
-
You may import % Complete for all mapped projects using the Integration > Import % Complete option, or for an individual project on the Cost Object > External Data tab. You can import the following percent complete types:
-
Cost % Complete
-
Performance % Complete
-
Performance % Complete (Units)
-
Schedule % Complete
-
Schedule % Complete (Units)
-
Units % Complete
-
EcoSys pulls % Complete from summarized data in P6. The projects for which % Complete are to be imported must first have been summarized (Tools, Summarize).