The Import % Complete screen within the Integration menu enables the user to run an import of % complete from P6.

  • You must create a custom field in EcoSys, to hold the % Complete values. This should be a Cost Object Level custom field.

  • You may import % Complete for all mapped projects using the Integration > Import % Complete option, or for an individual project on the Cost Object > External Data tab. You can import the following percent complete types:

    • Cost % Complete

    • Performance % Complete

    • Performance % Complete (Units)

    • Schedule % Complete

    • Schedule % Complete (Units)

    • Units % Complete

EcoSys pulls % Complete from summarized data in P6. The projects for which % Complete are to be imported must first have been summarized (Tools, Summarize).