Follow the procedure below to update the prioritization score of the opportunity.

  1. In the Opportunity Details panel, click the Prioritization Score tab.

  2. Click the ellipsis to select the required values for the following prioritization factors.

    • Growth – Select the weight for growth potential of the project.

    • Cost Efficiency – Select the weight for cost efficiency potential of the project.

    • Innovation – Select the weight for innovation potential of the project.

    • Risk Level – Select the weight for risk potential of the project.

    • Resource Impact – Select the weight for resource impact potential of the project.

    • Cost / Benefit – Select the weight of cost / benefit potential of the project.

  3. Click SAVE.

    The value in the Project Prioritization Score appears.

    • The formula used to calculate the Project Prioritization Score is:

      (Growth value selected*Growth Weight%) +

      (Cost Efficiency value selected*Cost Efficiency Weight%) +

      (Innovation value selected*Innovation Weight%) +

      (Risk Level value selected*Risk Level Weight%) +

      (Resource Impact value selected*Resource Impact Weight%) +

      (Cost/Benefit value selected*Cost /Benefit Weight%)

    • The values for the Growth weight, Cost Efficiency weight, Innovation weight, Risk Level weight, Resource Impact value weight, and Cost/Benefit value weight are set by the administrator.

    • When the Prioritization Score is updated, the Check: Prioritization Score validation check is completed

    • To view the updated Validation Count, click the Refresh icon. Once the Validation Count becomes zero the opportunity can be submitted for review.