The Project level Risks can be evaluated using Analysis tab. Based on the evaluation, the project risk to be promoted can be determined.
This procedure allows you to promote a Risk from Project to Portfolio. Once promoted, the Risk can be further developed.
-
Navigate to Portfolios > Risks.
-
Click the Actions list and select Promote Project Risk to Portfolio.
-
Click the Project ellipsis and select the project that contains the risk to be copied to portfolio.
Only the projects available under the selected portfolio are displayed.
-
Click the Project Risk ellipsis and select the project risk that you want to copy.
-
Type in the Risk Description.
-
Click RUN and then OK. In the Risk Register panel, the selected project risk gets copied along with its attributes.