The Project Selection Chart panel allows you to view the projects details in several charts. Follow the procedure below to view the charts.

  1. Navigate to Portfolios > Assignments.

  2. In the Project Selection Chart panel, click the Gantt tab. This displays the start date and end date of the all the projects of the portfolio in the gantt chart.

    • You can filter the projects by entering the start year or end year in the Filter box.

    • You can also view the projects in the gantt chart based on the timescale by selecting the required timescale from the Timescale Unit list.

    • You can also view the projects in the gantt chart based on the timescale by selecting the required timescale from the Timescale Subunit list.

  3. In the Project Selection Chart panel, click the S-Curve tab. The below listed budget details of the selected portfolio appear:

    • Original Budget

    • Current Budget

    • Current Forecast

    • Actuals

  4. In the Project Selection Chart panel, click the Forecast tab. This displays the forecast of the projects for all the available periods.

  5. In the Project Selection Chart panel, click the Disciplines tab. This displays the forecast of the projects for individual discipline.

  6. In the Project Selection Chart panel, click the Resources tab. This displays the following details in the bar chart:

    • Portfolio Hours: Displays the total hours forecast for all the projects in the portfolio.

    • Other Hours: Displays the difference between the total hours of all the portfolios and the portfolio hours of the selected portfolio.

    • Capacity: Displays the resource capacity added to the specific time period.

  7. Click the Analysis tab. The resource capacity of all the disciplines for each time period appears in the bar chart.

    SHARED Tip To view the resource capacity for an individual discipline, click the Discipline ellipsis and select the required discipline.

  8. Click the Bubble tab. This displays the project risk details as well as the current forecast of the project in the bubble chart.

    The details that appear in the bubble chart include:

    • Project ID: Displays the Project ID.

    • Project Score: Displays the project prioritization score.

    • Risk: Displays the portfolio score.