The Analysis tab provides the risk and action items data related to the selected portfolio risk and its project's risks.
Follow the procedure below to analyze the risk.
-
Navigate to Portfolios > Risks.
-
At the top of the screen, in the green parameter bar, click the Portfolio ellipsis to select the required portfolio.
-
Click the Analysis tab.
-
If required, click REFRESH to update the screen.
-
In the Project Risk Register panel, click the Project ellipsis and select the project for which you want to view the risks.
-
Click Refresh to update the screen.
-
In the Portfolio Risk Action Items panel, click the Risk ellipsis and select the risk for which you want to view the action items.
-
Click Refresh to update the screen.
-
In the Project Risk Action Items panel, click the Project and Risk ellipsis, and select the project and risk for which you want to view the action items.
-
Click Refresh to update the screen.