This procedure allows you to setup a stage gate as a stage gate activation step. Once this stage gate is approved during the stage gate process, the project becomes active.
Set a project activation gate only by using the Set Project Activation Gate action.
If a stage gate activation gate is not set; by default, the last stage gate is considered
as a stage gate activation step.
-
Navigate to Admin > Portfolios Admin > Stage Gates Admin.
-
Click the Actions list and select Set Project Activation Gate.
-
Click the Stage Gate Process ellipsis to select the required stage gate process.
-
Click the Stage Gate Activation Step ellipsis to select the required stage gate.
-
(Optional) Type a Comment.
-
Click RUN and then OK.